espa_top
How to Get Electricity for the First Time

How to Get Electricity for the First Time

What is needed to electrify an apartment building:

To electrify an apartment building, the required documents are:

  • Electricity application form (DEI form).
  • Certified copy of the Building Permit, with the stamp of the Urban Planning Service for the final electrification of the property. To begin the process, it is sufficient to submit a photocopy of the Urban Planning Document, simply certified for authenticity by a public or police authority, KEP, or by our service if the original is presented.
  • A clearance or space reservation for a substation from the relevant DEI service when the building exceeds 2,500m3, or an engineer's declaration for buildings smaller than 2,500m3 with full utilization of the building coefficient, where required. If there is a space reservation for a substation, the substation space contract (purchase or lease) must be signed before electrification.
  • Land plot survey, meter layout plan (basement and ground floor) for more than three meters, stamped and signed by an engineer, where required.
  • Elevator operation license, where required.

 

What is needed to electrify an apartment

To electrify an apartment, the required documents are:

  • Electricity application form (DEI form).
  • Certified copy of the Building Permit, with the stamp of the Urban Planning Service for the final electrification of the apartment, if it hasn’t already been submitted with the apartment building's file during initial electrification. To begin the process, it is sufficient to submit a photocopy of the Urban Planning Document, simply certified for authenticity.
  • Installer’s Declaration (ΥΔΕ) from a private electrician, either:
    • Endorsed by the relevant tax authorities (both the owner and electrician), for building permits issued before December 31, 1994.
    • Certificate from the owner’s tax authority, for building permits issued after December 31, 1994.
  • Declaration from the local municipality with the square meters for municipal tax, municipal fee, and real estate property tax.

 

What is needed to electrify a detached house

To electrify a detached house, the required documents are:

  • Electricity application form (DEI form).
  • Certified copy of the Building Permit, with the stamp of the Urban Planning Service for the final electrification of the property. To start the process, a photocopy certified for authenticity can be submitted.
  • Installer’s Declaration (ΥΔΕ) from a private electrician, either:
    • Endorsed by the relevant tax authorities for building permits issued before December 31, 1994.
    • Certificate from the owner’s tax authority for building permits issued after December 31, 1994.
  • Declaration from the local municipality with the square meters for municipal tax, municipal fee, and real estate property tax.


What is needed to electrify a commercial space, workshop, etc.

To electrify a commercial space, workshop, warehouse, etc., the required documents are:

  • Electricity application form (DEI form).
  • Certified copy of the Building Permit, with the stamp of the Urban Planning Service for the final electrification of the property. A photocopy certified for authenticity can be submitted.
  • Installer’s Declaration (ΥΔΕ) from a private electrician, either:
    • Endorsed by the relevant tax authorities for building permits issued before December 31, 1994.
    • Certificate from the owner’s tax authority for building permits issued after December 31, 1994.
  • Declaration from the local municipality with the square meters for municipal tax, municipal fee, and real estate property tax.
  • Installation and operation permit for production units (e.g., industrial and commercial units, warehouses), from the relevant industrial authority, in accordance with P.D. 84/84 and Law 2965/01, Article 6, Paragraph 8, where required.
  • Clearance or space reservation for a substation from the relevant DEI service when the building exceeds 2,500m3, or an engineer's declaration for smaller buildings with full building coefficient utilization, where required. If there is a space reservation for a substation, the substation space contract must be signed before electrification.


What is needed to electrify a building under construction

For construction work, a temporary construction site power supply is provided. The required documents are:

  • Electricity application form (DEI form).
  • Certified copy of the Building Permit, with the stamp of the Urban Planning Service for construction site use.
  • Installer’s Declaration (ΥΔΕ) for the construction site, without endorsement from the tax authority.
  • Declaration from the local municipality with the square meters for municipal tax, municipal fee, and real estate property tax.

 

What is an "electricity supply contract"

An electricity supply contract is the necessary agreement signed between the consumer and DEI to provide electricity to the property. It defines the relationship between the consumer and the supplier (DEI).

 

What is the advance payment against consumption

The advance payment is not a guarantee, but a partial payment for the electricity that is sold to the consumer, collected later due to technical reasons such as meter readings, bill issuance, and payment deadlines.

 

What are connection fees

DEI is required by Law 4483/65 (Article 8) to collect connection fees during initial electrification. According to the law, 20% of this fee is retained by DEI as a connection right, while the remaining 80% is deposited in the Bank of Greece as state revenue.

GET IN TOUCH

We are happy to answer any questions you might have, explore potential partnerships and receive requests from interested affiliates. Simply choose one of the available options and we'll get back to you in to time!

volttech.gr is using cookies!

We use cookies to offer you a personalized browsing experience.
Click on the 'Accept All' button and help us tailor our suggestions exclusively to the content you are interested in. Alternatively click on what you want and click 'Reject Not Selected'!

volttech.gr is using cookies!
Powered by NETMECHANICS